Project Description

CLIENT | Prosafe

VESSEL | Safe Concordia

DATE | June 2015

LOCATION | Brazil

Project Brief

CTS was invited by Prosafe to provide one Rope Access welding 6G team and two teams of R/A U.H.P. blasters & painters, for renewal of braces on the PS and SBS crane boom under the supervision and instructions of the maker’s Favelle Favco. The R/A blasting and coating team were to descale (Spot) the crane boom mechanically / clean chemically / U.H.P. W. Jet blasting and then paint after with 2 coats of primer and yellow top coat. CTS provided all the R/A equipment, consumables and the equipment’s required for the blasting and coating teams. Team was handpicked from our pool of skilled ex-shipyard pipe and steel fitters/welders with very good knowledge and relevant certificates. Experienced Blasting/Coating team were deployed for the project.

Scope of Work

Braces: Total renewal of 38 braces (26 on the port boom and 8 on the stbd boom)

• De-scaling and painting booms with two stripe coats of primer paint and top yellow coat full paint apply on booms

• CTS along with Prosafe, ensured area of works was clean of any debris and oil.

• All the passageway cleared from any obstacle for easy access.

• Hot Work area being minimised, and major cutting and welding done after approval from Safety inspector

• All electrical equipment checked by Prosafe electrical department and tagged ready to use

Project Gallery

Results

The project was delivered safely, within time and quality to the client.

Client Feedback

The client was extremely pleased and impressed with CTS quality of work and assured they would only use our services as and when required in the future.